With 19 years of experience in Piping, Mechanical Equipment, Storage Tanks, Steel Structures, and Quality Control activities in Construction, Oil & Gas sectors including Power Plant, Petrochemical Projects, and Refineries, I offer a wealth of expertise. As an effective Quality Engineer, I have a proven track record of driving continuous improvement initiatives. My focus and diligence are unmatched, and I am committed to fostering the corporate mission. Throughout my career, I have consistently been acknowledged for implementing actionable initiatives that reduce error rates and optimize company processes.
Overview
20
20
years of professional experience
3
3
years of post-secondary education
8
8
Certifications
Work History
Acting QA/QC Manager
ACWA Power Sirdarya
Shirin
6 2024 - Current
Reviewing of ITP, QAQC Procedures and Supplier QA/QC documents
Ensure that RFI Inspection Notification for Witness & Hold point required to be attended as per the ITP
Proficient in review of WPS/PQR & WPQ and QA/QC Dossier etc
According to Quality Management System and extensively implemented at all levels
Ensure that latest revision of drawing is available at site and controlled copy document is used at site
Ensure that the material receipt Inspection and monitoring the storage and preservation of the supplied items as per the requirements
Skill in international codes and standards ASME Sec I, Sec II, Sec V, Sec VIII Div 1, Sec IX, API 650, API 686, API 1104, ASME B 31.1, B 31.3, AWS D1.1/D1.2/D1.6
Ensure that the Quality Inspection reports are signed off by all based on the relevant RFIs
Ensure the testing activities of Welding & NDT are followed as per Specification & ITP
Incoming material Inspection control of Project materials and consumables
Involved in Erection and Inspection of Static and Rotating Equipment’s such as Vertical Vessels, Horizontal Vessels, Turbines, Compressor, Pumps & Field Erected Tank
Involved in Steel Structural Erection inspection activities.
Streamlined documentation processes for better tracking of QA/QC activities, improving overall transparency.
Coordinated internal audits for ISO certification, successfully maintaining compliance over multiple years.
Sr.QA/QC Engineer
ACWA Power Sirdarya
Shirin
01.2022 - 06.2024
Reviewing of ITP, QAQC Procedures and Supplier QA/QC documents
Ensure that RFI Inspection Notification for Witness & Hold point required to be attended as per the ITP
Proficient in review of WPS/PQR & WPQ and QA/QC Dossier etc
According to Quality Management System and extensively implemented at all levels
Ensure that latest revision of drawing is available at site and controlled copy document is used at site
Ensure that the material receipt Inspection and monitoring the storage and preservation of the supplied items as per the requirements
Skill in international codes and standards ASME Sec I, Sec II, Sec V, Sec VIII Div 1, Sec IX, API 650, API 686, API 1104, ASME B 31.1, B 31.3, AWS D1.1/D1.2/D1.6
Ensure that the Quality Inspection reports are signed off by all based on the relevant RFIs
Ensure the testing activities of Welding & NDT are followed as per Specification & ITP
Incoming material Inspection control of Project materials and consumables
Involved in Erection and Inspection of Static and Rotating Equipment’s such as Vertical Vessels, Horizontal Vessels, Turbines, Compressor, Pumps & Field Erected Tank
Involved in Steel Structural Erection inspection activities.
QA/QC Engineer – Mechanical
Arabian Industries Project LLC
06.2018 - 11.2021
Incoming material Inspection of project materials and consumables
Review client specifications to identify the Piping & Pipeline Welding procedure requirements
Involved Erection and Inspection of GTG, HRSG, Static and Rotating Equipments such as Vertical Vessels, Horizontal Vessels, Pumps & Field Erected Tank etc
Involved in Steel Structural Erection inspection activities
Involved in receiving inspection of Equipments
Co-ordination with client to make clearance for Erection
Inspection of Foundation Padding level checking as per IFC drawing prior to install the Equipment
Alignment Inspection of Vertical & Horizontal Static Equipments to release for Grouting
Foundation Bolt Tightening Inspection of Static Equipment upon completion of Grouting
Inspection of Internal and External accessories installation as per IFC drawing
Final Box-up Inspection of Static Equipment’s upon completion of all discipline works
Preliminary & Final shaft Alignment inspection of GTG, Pumps and Blowers
Coordinates with site welding inspector coating inspector for pipe book updates
Prepares inspection report and submit to the company for review and approval
Coordinates with the clients to request the schedule for inspection
Review of final documentation MC and PC Dossier.
QA/QC Engineer – Mechanical
Dodsal Engineering & Construction PTE Ltd.
Abdali, Kuwait
03.2016 - 03.2018
Involved Erection and Inspection of Static and Rotating Equipments such as Vertical Vessels, Horizontal Vessels, Pumps and Compressors
Involved in stage wise Inspection of Field Erected Storage Tanks
Involved in Steel Structural Erection inspection activities
Involved in receiving inspection of Equipments and Tank parts
Co-ordination with client and PMC to make clearance for Erection
Involved in Shaft alignment Inspection of HP Boiler Feed water pumps, Reciprocating pumps, Generator, EOT Crane etc
Review of Quality documents like ITP, QC Procedure, Checklist and protocol for equipments
Inspection of Foundation Padding level checking as per IFC drawing prior to install the Equipment
Alignment Inspection of Vertical & Horizontal Static Equipments to release for Grouting
Foundation Bolt Tightening Inspection of Static Equipment upon completion of Grouting
Inspection of Internal and External accessories installation as per IFC drawing
Final Box-up Inspection of Static Equipments upon completion all discipline works
Installation and inspection of Rotary equipment’s such as padding, Elevation, Position, Orientation, Levelling, and Preliminary Shaft Alignment to release for the Grouting
Foundation Bolt Tightening Inspection of Rotating Equipment upon completion of Grouting
Inspection of Final Shaft Alignment inspection without piping connection and with piping connection for the Suction & Discharge Nozzles of Rotating Equipments
Preparation of all Inspection reports as per approved ITP
Inspect the Tanks fit-up, peaking, and banding, roundness and weld visual inspections as per the project requirements
Following NDE requirements of Tanks as per Client Specification and API 650
Radiographic Film Interpretation and co-ordination with NDT Co-ordinator & Client
Inspection of Tanks Hydrostatic, Pneumatic, Vacuum box & Roof air leak test and prepare the reports.
QC Engineer – Mechanical
G S Construction Saudi Arabia
10.2014 - 01.2016
Involved in installation and inspection of Static and Rotatory Equipment
Involved in inspection of Static Equipments like Super heaters, Economizers, Sulphur burner, Waste heat boiler, Air filter, pump boot, pump tanks, Air coolers, Pre-heaters, Acid cooler, Heaters, Leaf filters, Candle Filters, Deaerator, Surface condenser, Condensate tank, Strainers, Oil tank, Oil Cooler, Heat Exchanger, Cold Exchanger etc
Involved in inspection of Rotating equipments like Centrifugal pumps, Submersible pumps, Reciprocating pumps, HP BFW pumps, HP turbine pumps, Turbines, Generator, EOT crane etc
Review of quality documents like ITP, QC procedure, checklist and protocol for equipments
Raise RFI (Request for field inspection) to client for inspection of foundation level and taking over
Foundation level check as per IFC drawings, co-ordination and released for equipment erection
Installation and inspection of static equipment’s includes padding, Elevation, Position, Orientation, Verticality and Levelness
Installation and inspection of rotary equipment’s includes padding, Elevation, Position, Orientation, Levelness, Pre-shaft alignment, run out and dialing
Final inspection of static equipment as per checklist and released for painting/insulation
Shaft alignment checking of pumps before and after piping and making final reports
Preparing protocol and final handing over of equipment’s to client
Involved in Steel Structural Erection inspection activities
Stage wise Inspection of Tank fabrication, erection and weld visual Inspection as per ITP and Project Specification, such as floating roof and cone roof in various diameters
Review method statements, ITP’s
Conduct PQR/Welders Qualification Test
Compile the documents and reports for final acceptance of Clients, Consultants and third party
Review Raw materials test certificate
Storage and handling of welding consumables Inspection
NDE requirements are monitoring
Radiographic Film Interpretation and co-ordination with NDT persons & Client
Hydrostatic and pneumatic tests are observed and reported, including vacuum box testing.
Manager – QA/QC (Equipments & Tanks)
Reliance Industries Ltd
12.2013 - 10.2014
Review of QC Plan & Test Procedure for the Sub-Contractors related to Steel Structural, Equipments & Tanks
Co-ordination of all inspection with Sub-Contractor
Attending Weekly QA/QC meeting with Contractor
Coordination of NDT / PWHT activities with INSPECTION
Attending Test Pack Review meeting with Contactor
Review of NDT progress reports (PT, MT, and PWHT & Hardness) monthly for invoicing
Review of weekly welder acceptable percentage report
Controlling of NDT check percentage as per project Spec., NDT Summary (Weekly/Monthly)
Final clearance after Hydro Test.
QC Engineer - Mechanical
Dodsal Engineering & Construction PTE Ltd.
04.2012 - 10.2013
Review the ITP’s, Quality procedures and dossiers
Inspection of incoming raw material
Inspect the welding consumables, filler material compare with required standard and releasing for production
Review of WPS, PQR and witnessing of Welder qualification Test
Fit-up and welding inspection of piping and Steel Structural components
Inspect the Tank fit-up, peaking, bending, roundness and weld visual inspections as per the project requirements
Inspection of welding equipments and baking ovens
Monitor the Welding parameters
Inspection of pre heat value in low alloy material as per the specification
Witness PWHT activity and review the graph records
Witnessing Dye Penetrate Testing, and UT Thickness Measurement
Interpretation of radiography films and evaluates to minimize the rejection
Ensure Welding works are performed as per Welding Procedure Specification
Making surveillance during welding to ensure that a Qualified Personnel carries out work using controlled parameters and correct consumables according to procedure
Carry out the DPT & MPT witness inspection of reinforcement pad and structural components
Carry out the vacuum box testing witness of the bottom plates
Generating NCR’s in case of violations and monitoring corrective actions
Reviewing weekly reports and maintaining records
Review of hydro test packages and witnessing hydrostatic and pneumatic testing
Witnessing the NDT activities are carried out as per project requirement
Issuing the punch points prior to the Hydro test
During insulation, stage wise inspection like a surface preparation, insulation and cladding
Co-ordinate with client, third party inspectors & Project management Team
Preparing Final QA/ QC documents and submit the final dossier to the client.
Senior QC Engineer – Mechanical
M/S Punj Lloyd Ltd.
10.2010 - 03.2012
Inspection of Crude Oil storage tanks as per API 650
Responsible for Welding & Quality control works of Crude Oil Storage Tanks
Conduct PQR/Welders Qualification Test
Compile the documents and reports for final acceptance of Client and third party
Inspection of all incoming materials related to Project
Daily inspection coordination with client, third party
Preparation of test packs and submission for approval.
Engineer QA/QC – Mechanical
M/S Punj Lloyd Ltd.
11.2009 - 09.2010
Prepare the ITP’s, Quality procedures and dossiers
Inspection of incoming raw material
Inspect the welding consumables, filler material compare with required standard and releasing for production
Review of WPS, PQR and witnessing of Welder qualification Test
Fit-up and welding inspection of piping and Steel Structural components
Inspect the Tank fit-up, peaking, bending, roundness and weld visual inspections as per the project requirements
Monitor the Welding parameters.
QC Inspector – Mechanical
M/S Arabian Pipe Company Saudi Arabia.
08.2007 - 08.2009
Daily monitoring of welding quality of pipe in all plant & maintain the database for Repair, Cut-off, and Rejection related to welding
Whenever the welding quality exceeds the qualitative target, Analyze the variables which cause for the same & make troubleshooting with the concerned in charge
Conducting Welding related Trainings for Welders & Welding Operators
Conducting trial welding with the new welding consumable and analyze the results with respect to applicable standards/specification.
QC Engineer - Mechanical
M/S Punj Lloyd Ltd.
10.2004 - 07.2007
Involved in installation and inspection of Static and Rotatory Equipment
Involved in inspection of Static Equipments like Super heaters, Economizers, Sulphur burner, Waste heat boiler, Air filter, pump boot, pump tanks, Air coolers etc
Review the ITP’s, Quality procedures and dossiers
Inspection of incoming raw material
Inspect the welding consumables, filler material compare with required standard and releasing for production
Review of WPS, PQR and witnessing of Welder qualification Test
Fit-up and welding inspection of piping and Steel Structural components.
Education
Bachelor of Technology - Mechanical Engineering
Janardan Rai Nagar Rajasthan Vidyapeeth
Rajasthan
07.2012 - 02.2015
Skills
Quality improvement plans
Problem-solving aptitude
Decision-Making
Team Leadership
History
ACWA Power Sirdarya, Acting QA/QC Manager, Jun 2024 to Present, Uzbekistan Sirdarya 1500 MW CCGT Power Project, ACWA Power
ACWA Power Sirdarya, Sr.QA/QC Engineer, Jan 2022 to Jun 2024, Uzbekistan Sirdarya 1500 MW CCGT Power Project, ACWA Power
Arabian Industries Project LLC, QA/QC Engineer – Mechanical, Jun 2018 to Nov 2021, Construction Services for Yibal Khuff Project, Petroleum Development Oman LLC (PDO)
Dodsal Engineering & Construction PTE Ltd., QA/QC Engineer – Mechanical, Mar 2016 to Mar 2018, New Gathering Centre, GC-31(North Kuwait), Kuwait Oil Company (KOC)
G S Construction Saudi Arabia, QC Engineer – Mechanical, Oct 2014 to Jan 2016, Rabigh II Refining & Petrochemical Project (CP3/CP4), Saudi Aramco & Sumitomo Chemical
Reliance Industries Ltd, Manager – QA/QC (Equipments & Tanks), Dec 2013 to Oct 2014, Reliance Jamnagar Phase-3 (J3), Reliance Industries Ltd
Dodsal Engineering & Construction PTE Ltd., QC Engineer - Mechanical, Apr 2012 to Oct 2013, Habshan Sulphur Granulation Plant Project, Abu Dhabi Gas Industries Limited (GASCO)
M/S Punj Lloyd Ltd., Senior QC Engineer – Mechanical, Oct 2010 to Mar 2012, Crude Oil Storage Tanks Terminal Project
M/S Punj Lloyd Ltd., Engineer QA/QC – Mechanical, Nov 2009 to Sep 2010, Neptha Cracker Project Panipat (Haryana)
M/S Arabian Pipe Company Saudi Arabia, QC Inspector – Mechanical, Aug 2007 to Aug 2009, SAW Pipe Mill
M/S Punj Lloyd Ltd., QC Engineer - Mechanical, Oct 2004 to Jul 2007, Hydro Cracker Project Panipat (Haryana)